Planning Inspector allows permission for new Northamptonshire solar farm

Pegasus Group, on behalf of JBM Solar Projects 20 Limited, has secured planning permission on appeal for a new solar farm and battery stations outside the village of Greatworth, five miles east of Banbury, Northamptonshire.

The outline proposal, which will produce enough clean renewable energy to power the equivalent electricity needs of over 18,000 homes a year, was initially refused planning permission by West Northamptonshire Council in October 2022 on the grounds of adverse effect on the landscape and visual character of the area and conflict with the development plan.

The scheme was heard at Public Inquiry in June 2023, with community group Copse Lodge Action Group also appearing formally (known as a Rule 6 party).

The Inspector’s report acknowledged that the proposal would harm the landscape character and would conflict with the development plan, but that the very significant weight arising from renewable energy production and storage, along with significant biodiversity enhancements, outweighed the identified harm.

The proposal will give rise to significant environmental and ecological benefits through habitat enhancements and carbon emission savings. It will generate economic benefits with an injection of £30m into the local economy and the creation of 70-80 temporary jobs during the construction phase. The scheme also will provide an outdoor classroom and permissive route through the site to boost education and understanding about the renewable energy sector.

Conor McAllister of JBM Solar Projects 20 Ltd said: “It’s fantastic to get this result, particularly after many years of hard work from all involved. Renewable energy projects can too often meet resistance but we are committed to working collaboratively with the council to progress the scheme and deliver it promptly.”

Ellen Fortt, Senior Planner at Pegasus Group, added: “This appeal decision demonstrates the significant weight that renewable energy schemes hold in the planning balance, reinforcing their role in the country’s efforts to reach net zero by 2050. We are pleased to be able to advise on valuable and hugely beneficial projects like this.”

Work is expected to start on site in Autumn 2024. Pegasus Group led on matters of planning, landscape and heritage, alongside No5 Chambers as Counsel and Avian Ecology.

A message from the Editor:

Thank you for reading this story on our news site - please take a moment to read this important message:

As you know, our aim is to bring you, the reader, an editorially led news site and magazine but journalism costs money and we rely on advertising, print and digital revenues to help to support them.

With the Covid-19 pandemic having a major impact on our industry as a whole, the advertising revenues we normally receive, which helps us cover the cost of our journalists and this website, have been drastically affected.

As such we need your help. If you can support our news sites/magazines with either a small donation of even £1, or a subscription to our magazine, which costs just £33.60 per year, (inc p&P and mailed direct to your door) your generosity will help us weather the storm and continue in our quest to deliver quality journalism.

As a subscriber, you will have unlimited access to our web site and magazine. You'll also be offered VIP invitations to our events, preferential rates to all our awards and get access to exclusive newsletters and content.

Just click here to subscribe and in the meantime may I wish you the very best.









Latest news

Related news

By continuing to use the site, you agree to the use of cookies. more information

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close